Back Cove South Storage Facility

PROJECT UPDATE: 

Weekly updates below:



Week of February 21st

The next phase of the Back Cove South Storage Facility Project will begin Wednesday, February 24 with the preparation for pipe installation in Preble Street, from the Back Cove soccer fields to Baxter Boulevard. Traffic control devices will be installed to provide for a safe work environment within the street ROW and will be adjusted daily as work progresses. Please adjust your driving accordingly when progressing through an active construction area. For more information please visit the Public Works website.

traffic control plan Page_2
traffic control plan Page_2

For the week ending February 5, 2021.

It was another active week as contractor N.S. Giles completed the second concrete pour of the project on February 4th with 843 cy of concrete being delivered by 85 Auburn Concrete trucks for part of the Tank #1 base slab.

Sargent continues on the northern excavation of the sump area with the removal of soils and the installation of additional steel bracing.

N.S. Giles and Bill Dixon Rebar have begun the third rebar frame/ matting for the continued base of Tank #4.


Click this link for a video of the concrete pour.  https://youtu.be/vtnt-yDzB8Q

BCSSF 2021-02-04 DSCF0088 digging in mud
BCSSF 2021-02-04 DSCF0095 More people working
BCSSF 2021-02-04 DSCF0082 cranes operating
BCSSF 2021-02-04 DSCF0081 People working

For the week ending January 29, 2021

The City's contractor, Sargent Corporation, continues work on the northern excavation of the sump area with the removal of soils and the installation of additional steel bracing.

Everyone watches the first concrete pour cure.

And the primary subs onsite, N.S. Giles and Bill Dixon Rebar, continue with the preparation of the next rebar frame/ matting for our second pour next week.

Concrete Pour
A view from the top
Concrete drying
Structural steel framing
Watching the concrete pour

For the week ending January 22, 2021

The City's contractor, Sargent Corporation, and N.S. Giles, our concrete subcontractor, hit a major milestone this week with the first concrete pour of the project within Tank #4. Starting under lights in the early morning, 780 cubic yards (78 truck loads) were delivered to the site on Wednesday. With over 40 people onsite either actively working or inspecting/ observing the operation went smoothly and everyone walked away from the day with a sense of accomplishment. This first pour represents approximately 5% of the total concrete that will be placed for the project.

On the other end of the excavation, the placement of the rebar matting began for Tank #1.

Overview of site at night
workers prepare for concrete pour
First Concrete Pour photo 1
First Concrete Pour photo 2
First Concrete Pour photo 3

For the week ending January 15, 2021.

The City's contractor, Sargent Corporation, has completed the placement of the gravel borrow that will serve as the base for the tanks.

N.S. Giles, our concrete subcontractor, continues with the placement of the rebar matting for Tank #4.

The first concrete pour should be next week.

Rebar cage
Rebar cage
Temporary forms for the concrete pour
Temorary forms for the concrete pour
Water infiltration through the sheet piles.  We continue to pump 24/7
water infiltration through the sheet piles
Waterstop being secured
Waterstop being secured
Stone for fine grading of the base
Stone for fine grading of the base

Week of January 10, 2021 

The City's contractor, Sargent Corporation, has completed the excavation with the exception of the deep sumps at either end. 

The placement of the gravel borrow that will serve as the base for the tanks continues. 

N.S. Giles, our concrete subcontractor, has mobilized to the site. 

The NS Giles crew has begun the placement of the rebar matting for Tank #4. 

The City Council has approved an easement to bring CMP power onto the site.

Construction photo 2 2021-01-08
Construction photo 3 2021-01-08
Construction photo 4 2021-01-08
Construction photo 1 2021-01-08

Week ending December 18, 2020

Construction activities were slower this week as the project was dealing with vandalism which destroyed equipment and pumps over the past weekend and the snow event Thursday. Once resumed, active placement of the granular material continued. This material will serve as the base for the tanks and numerous geotechnical engineers visited the site to evaluate the material and compaction efforts. Two concrete spanning beams were placed to provide additional bracing at the bottom of the excavation between the sheet pile walls.

The team at Sebago Technics, which is providing our project oversight and inspection services, also provided us this week with the below link to aerial drone footage from the site.

https://www.youtube.com/watch?v=zEz-JCCNmZU


Dump Truck
Concrete Beam
Active Construction photo
Concrete support Beam

Week of December 13, 2020: The City's contractor, Sargent Corporation, has reached the bottom of the excavation and has begun placing the granular material which the concrete tank will sit upon.

BCSSF 2020-12-08 DSCF9963
BCSSF 2020-12-08 DSCF9957
BCSSF 2020-12-08 DSCF9959

Week of November 30, 2020: The BCSSF hit a milestone last week with the completion of the sheet pile support bracing. Excavation continues from the mid-level steel bracing (Elevation -14) to the bottom of the proposed concrete slab (El. -25).

BCSSF 2020-12-01 DSCF9949
BCSSF 2020-12-01 DSCF9947
BCSSF 2020-12-03 DSCF9951
BCSSF 2020-11-17 Public Update 2_Page_1
BCSSF 2020-11-17 Public Update 2_Page_2
BCSSF 2020-11-17 Public Update 2_Page_3
BCSSF 2020-09-18 September Fact Sheet Update_Page_1

PRESS RELEASES

Date Notice Additional Documents
05/07/2018 Geo-Technical Work Notice
09/06/2019 Geo-Technical Work Notice
11/07/2019 Neighborhood Meeting Notice Meeting Notice
04/15/2020 Sargent Phase 1B TCP and Site Layout Plan
07/13/2020 Maine DEP - Finding of No Significant Impact FONSI
BCSSF 2019-02-26 Public Information Sign