Back Cove West Storage Conduit

The project is under construction by Sargent Corporation from Stillwater, ME. Construction will continue throughout 2021, 2022 and 2023.

Construction Updates and Photos

Condensed Construction Schedule (Updated 03/28/22)

BCWSC 2022-03-28 Sargent - BCW - Project Schedule - Rev. 4C

An updated (03/28/2022) full construction schedule can be viewed here: SCHEDULE

**MAJOR TRAFFIC ALERT** Baxter Boulevard Traffic Impacts

Sargent will be closing more of Baxter Boulevard, from Payson Park to Dartmouth Street.  This closure will begin 9/7/2021 and last until December 2022.

See below for a map of the closure as well as for more information about the project.

BCWSC Sargent 2021-09-07 Traffic Control Plan Phase 2 Opens in new window


**MAJOR TRAFFIC ALERT** Baxter Boulevard Traffic Impacts Begin June 24

Sargent will be closing Baxter Boulevard from Payson Park to Vannah Avenue. This first phase of closure is scheduled to last for the next three months. 

See below for a map of the closure as well as for more information about the project.

BCWSC Sargent 2021-05-06 Traffic Control Plan Phase 1

Sargent Corporation was the low bidder with a bid of $27,272,257.00

The Notice of Award was issued on December 28, 2020 and signed on December 29, 2020.

City of Portland's Planning Authority has approved a Level 1 Site Alteration Permit on December 30, 2020. 

Maine DEP has issued a Finding of No Significant Impact for the Back Cove West Storage Conduit Project.  The report has been posted below under Press Releases. 

On March 4, 2020 the City of Portland had a neighborhood meeting on this project.  The presentation given at the meeting can be found under Press Releases.

Related Documents

PRESS RELEASES

Date Notice Additional Documents
02/19/2020 Neighborhood Meeting Notice Meeting Notice
03/04/2020 Neighborhood Meeting Presentation Presentation
04/07/2020 Maine DEP - Finding of No Significant Impact FONSI
BCWSC 2021-08-26 Public Information Sign

WHAT’S HAPPENING                  

  • 2.25 Million Gallon Underground Storage Conduit.
  • New 1,690 foot long 20 foot x 8 foot box conduit will be installed in Baxter Boulevard to capture Combined Sewer Overflows before they reach back Cove.
  • 2,133 feet of 60" round pipe to be used for storage.
  • 8 existing CSO’s will be consolidated into 2 remaining CSO’s.
  • New sewer, storm drains and water lines will be installed in Dartmouth Street from Baxter Boulevard to Forest Avenue.
  • Streets within work area will be reconstructed, new pavement installed.
  • Multiple storm drain outfalls will be replaced along Baxter Boulevard.
  • Multiple long street closures will occur throughout the project.
  • New traffic signal at Vannah Ave and Baxter Blvd.

WHAT TO EXPECT DURING THE PROJECT

  • Noise
  • Large equipment and machines moving through the area creating vibrations
  • Traffic disruptions, backups, moving work-zone, slower traffic
  • Streets will be closed
  • Temporary disruptions to driveways, water, sewer lines (contractor must provide notification)
  • Temporary water lines will be installed running across yards and connecting to houses
  • Dust - contractor required to control dust but it will still get dusty at times
  • Professional interactions with contractor (contact one of the people listed below, if this doesn’t happen)

SEQUENCING OF PROJECT

  1. Start of construction July 2021 and continue through 2022.
  2. Project will start by closing Baxter Boulevard from Payson Park to Vannah Avenue.
  3. Once the work progresses towards Vannah Avenue Baxter Boulevard will be closed from Payson Park to Dartmouth Street from September 2021 to December 2022.
  4. A 20 foot x 8 foot concrete box conduit will be installed from Cheverus Track to Mackworth St.
  5. 60" storage pipe will be installed from Mackworth St to Dartmouth Street.
  6. Base paving first of December 2022.
  7. Once this section is complete Dartmouth St will be closed from Forest Ave to Baxter Boulevard in March of 2023 to November 2023.
  8. New sewer, storm and water will be installed in Dartmouth Street.                             
  9. Spring 2024 Surface Paving and stripping of the streets.

WHO TO CONTACT WITH QUESTIONS/ISSUES

  • Project Engineer, Portland Department of Public Works: Nathaniel Smith at (207) 874-8818, nhs@portlandmaine.gov
Aerial Location Map of the Project